South Pekin Road Construction Will Start Monday, August 19th. Click here for more information.

Starting on August 19th through the end of September of 2024, South Pekin will be under construction. Please expect delays and use alternate route. 

Construction will occur between 5th street and Davidson Ave along South Pekin Road.

Schedule Highlights:

  • Week of 8/19: Mobilize and start work on ADA Ramps
  • Week of 8/26 & 9/1: ADA Ramp work
  • Week of 9/9: Complete ADA Ramps, Grind Rodeway, Roadway Repairs
  • Week of 9/16: Complete Repairs, Start Paving
  • Week of 9/23: Pavement Cure, Striping, Roadside Restoration
  • Week of 9/30: Project Completion

For more information, please contact Public Works 360-225-7999.