W. Scott Ave Projects Notification
May 5, 2023
Please read below for more information about upcoming projects on W. Scott Avenue.
- Project No. 1 - W. Scott Avenue Asbestos Cement Waterline Replacement
- Project No. 2 - W. Scott Avenue Road Full Depth Reclamation from Pacific to RR tracks
- Project No. 3 - W. Scott Avenue/Guild Road from RR tracks to Schurman Way
Project No. 1 - W. Scott Avenue Asbestos Cement Waterline Replacement
- Advertisement for Bids went out April 2023
- City Council Approved the Lowest Bidder May 1, 2023
- Start of Construction approximately May 15, 2023
- Substantial completion July 28, 2023
- Final Completion 2 weeks after substantial completion
Project No. 2 and 3 - Guild Road and West Scott Avenue Improvements
- Advertisement May 10- 24, 2023
- Start Construction Approximately June 19, 2023
- Substantial Completion Approximately November 10, 2023
- Final Completion 2 weeks after Substantial Completion
We will not have any full road closures, only partial lane closures. We will keep access open to your business or residence during the construction projects and be in direct communication with you and share what week we will be working along your property line. If your residential home has one driveway, we will need to block your driveway as we pour and allow for cure time. We will work with you during this time.
Please reach out to us directly if you have any questions. Public Works 360-225-7999
Riley Bunnell | Director | 360-225-7999, ext 201 | bunnellr@ci.woodland.wa.us |